Abstract
A new mathematical treatment of alarms that considers them as multi-variable interactions between process variables has provided the first-ever method to calculate values for alarm limits. This has resulted in substantial reductions in false alarms and hence in alarm annunciation rates in field trials. It has also unified alarm management, process control and product quality control into a single mathematical framework so that operations improvement and hence economic benefits are obtained at the same time as increased process safety. Additionally, an algorithm has been developed that advises what changes should be made to Manipulable process variables to clear an alarm. The multi-variable Best Operating Zone at the heart of the method is derived from existing historical data using equation-free methods. It does not require a first-principles process model or an expensive series of process identification experiments. Integral with the method is a new format Process Operator Display that uses only existing variables to fully describe the multi-variable operating space. This combination of features makes it an affordable and maintainable solution for small plants and single items of equipment as well as for the largest plants. In many cases, it also provides the justification for the investments about to be made or already made in process historian systems. Field Trials have been and are being conducted at IneosChlor and Mallinckrodt Chemicals, both in the UK, of the new geometric process control (GPC) method for improving the quality of both process operations and product by providing Process Alarms and Alerts of much high quality than ever before. The paper describes the methods used, including a simple visual method for Alarm Rationalisation that quickly delivers large sets of Consistent Alarm Limits, and the extension to full Alert Management with highlights from the Field Trials to indicate the overall effectiveness of the method in practice.
Similar articles
-
PT-SAFE: a software tool for development and annunciation of medical audible alarms.Anesth Analg. 2012 Mar;114(3):576-83. doi: 10.1213/ANE.0b013e3182456963. Epub 2012 Feb 6. Anesth Analg. 2012. PMID: 22312124
-
Monitor alarm fatigue: standardizing use of physiological monitors and decreasing nuisance alarms.Am J Crit Care. 2010 Jan;19(1):28-34; quiz 35. doi: 10.4037/ajcc2010651. Am J Crit Care. 2010. PMID: 20045845
-
Should we be alarmed by our alarms?Curr Opin Anaesthesiol. 2007 Dec;20(6):590-4. doi: 10.1097/ACO.0b013e3282f10dff. Curr Opin Anaesthesiol. 2007. PMID: 17989556 Review.
-
The hazards of alarm overload. Keeping excessive physiologic monitoring alarms from impeding care.Health Devices. 2007 Mar;36(3):73-83. Health Devices. 2007. PMID: 17500263
-
Safety and nutritional assessment of GM plants and derived food and feed: the role of animal feeding trials.Food Chem Toxicol. 2008 Mar;46 Suppl 1:S2-70. doi: 10.1016/j.fct.2008.02.008. Epub 2008 Feb 13. Food Chem Toxicol. 2008. PMID: 18328408 Review.
Cited by
-
Pre-Warning for the Remaining Time to Alarm Based on Variation Rates and Mixture Entropies.Entropy (Basel). 2025 Jul 9;27(7):736. doi: 10.3390/e27070736. Entropy (Basel). 2025. PMID: 40724452 Free PMC article.
Publication types
MeSH terms
LinkOut - more resources
Full Text Sources
Other Literature Sources