A construction project scheduling methodology considering COVID-19 pandemic measures
- PMID: 35249628
- PMCID: PMC8648395
- DOI: 10.1016/j.jsr.2021.11.007
A construction project scheduling methodology considering COVID-19 pandemic measures
Abstract
Introduction: At the beginning of the COVID-19 pandemic, various social measures were taken and various sectors were affected with strict precautions and safety measurements. The construction industry, where numerous employees work together, was affected by these COVID restrictions. The pandemic period typically further delayed the construction contracts.
Methods: This study addresses the project duration, pandemic risk, and project cost of a construction project case by using both multi-objective genetic algorithm and resource constrained project scheduling techniques, using modeling of COVID-19 infection rate. Finally, the analytic hierarchy process (AHP), a multi-objective technique, is used to obtain an optimal solution using three criteria: project duration, total cost, and pandemic risk value.
Results: A case study is used for analyzing the outcomes of the pandemic-based modeling, the original schedule of the case study ends in 46 days. Feasible schedules are obtained with durations occurring between 61 to 199 days, the pandemic risks range from 46% to 89%, and the total cost varies from 174,669.8 Turkish Lira (TL) to 186,126.7 TL. Consequently, the most optimal-final solution is obtained Alternative 5 (0.46% pandemic risk, 199 Day (10 workers) with 185,722 TL).
Conclusion: We conclude that the possible rate of pandemic-related delays can be obtained by using both these techniques and the infection modeling method. Using the COVID-19 infection rate modeling, duration and cost changes are calculated by considering infection risk in construction workers. Practical Applications: Using the COVID-19 infection rate modeling, project delays and cost overruns are determined by considering infection risk in construction workers. Optimum worker sizes and delayed construction activities are determined according to the selected solution by using the AHP technique. Expectedly, this study may help determine the construction process while preserving social distances between construction workers during pandemic situations like COVID-19.
Keywords: AHP; COVID-19; Multi-objective optimization; OHS; Pandemic.
Copyright © 2021.
Figures








Similar articles
-
Early Impacts of the COVID-19 Pandemic on the United States Construction Industry.Int J Environ Res Public Health. 2021 Feb 6;18(4):1559. doi: 10.3390/ijerph18041559. Int J Environ Res Public Health. 2021. PMID: 33562127 Free PMC article.
-
Estimated Association of Construction Work With Risks of COVID-19 Infection and Hospitalization in Texas.JAMA Netw Open. 2020 Oct 1;3(10):e2026373. doi: 10.1001/jamanetworkopen.2020.26373. JAMA Netw Open. 2020. PMID: 33119111 Free PMC article.
-
Worker Perspectives on COVID-19 Risks: A Qualitative Study of Latino Construction Workers in Oakland, California.Int J Environ Res Public Health. 2022 Aug 9;19(16):9822. doi: 10.3390/ijerph19169822. Int J Environ Res Public Health. 2022. PMID: 36011454 Free PMC article.
-
COVID-19 and suicide risk in the construction sector: preparing for a perfect storm.Scand J Public Health. 2021 Nov;49(7):774-778. doi: 10.1177/1403494821993707. Epub 2021 Feb 18. Scand J Public Health. 2021. PMID: 33596728 Review.
-
Factors influencing the timely completion of construction projects in Sri Lanka.PLoS One. 2022 Dec 15;17(12):e0278318. doi: 10.1371/journal.pone.0278318. eCollection 2022. PLoS One. 2022. PMID: 36520802 Free PMC article. Review.
Cited by
-
Facility planning and schedule design in the pandemic: Eliminating contacts at construction workplace.J Clean Prod. 2023 Apr 1;395:136394. doi: 10.1016/j.jclepro.2023.136394. Epub 2023 Feb 10. J Clean Prod. 2023. PMID: 36789403 Free PMC article.
-
Workforce scheduling efficiency assessment in construction projects through a multi-objective optimization model in the COVID-19 context.Heliyon. 2023 Jun;9(6):e16745. doi: 10.1016/j.heliyon.2023.e16745. Epub 2023 Jun 3. Heliyon. 2023. PMID: 37292343 Free PMC article.
References
-
- Administration, O. S. and H. (2020). COVID-19 Guidance for the Construction Workforce. https://www.osha.gov/sites/default/files/publications/OSHA4000.pdf.
-
- Aile Çalışma ve Sosyal Güvenlik Bakanlığı . Aile Çalışma ve Sosyal Güvenlik Bakanlığı; Labour and Social Services): 2020. Aile ve Sosyal Politikalar Bakanlığı Yayını (Bulletin of Ministry of Family. https://www.ailevecalisma.gov.tr/media/41607/alo-170-covi-d-sss-stodb-06....
-
- Aile Çalışma ve Sosyal Güvenlik Bakanlığı. (2020b). Yapı İşyerlerinde Yeni Tip Koronavirus Kontrol Listesi (A Check List For A New-Type Coronavirus in Construction Works). https://ailevecalisma.gov.tr/media/47843/intes_kontrol_listesi_20200611.pdf
-
- Akçalı, Ü. (2020). 2020 Yılı İnşaat Birim Fiyat Analizleri I-II.
-
- Alenezi T.A.N. Covid-19 causes of delays on construction projects in Kuwait. International Journal Of Engineering Research and General Science. 2020;8(4):35–39.
MeSH terms
LinkOut - more resources
Full Text Sources
Medical